Friday, January 8, 2010

Happy New Year!

During the last month, the construction details have began to transform the remodel. On the exterior, the contractor has been installing siding and putting up the trellis supports. The ledger support for the elevated deck, on the east side of the house, has been installed and the concrete deck post footings have been poured.



The interior has also been taking shape. Drywall has been installed and is being prepped for paint. Scaffold work has enabled the drywall subcontractor to reach the high vaulted ceiling and the skylight wells are bringing daylight into the upper floor spaces. The tile sub-contractor has started the preparations for the interior tile work on the Kitchen and Dining Room tile floors as well as the Master Bathroom, walk-in shower.





Kitchen cabinets have also been delivered and installed, but are presently hiding behind plastic sheeting to protect them from the drywall sanding dust.